Twin new transformers which weigh 64,000 kg each were delivered into the new Silverdale Substation in Mission, BC. Access into the Under Construction Substation was extremely tight and had both vertical and horizontal curves in the road which prevented access by conventional highway trailers. A shortened trailer and our hydraulic lifting fifth wheel tractor were used to bring the transformers on-site. Maneuverability of crews and equipment required particular care and planning as the construction of the substation was in full swing with several contractors occupying the site.
Project Highlights:
Services:
North Vancouver residents watched the new Spirit Trail Pedestrian/Cyclist Pathway near completion with the installation of the new Pedestrian Bridge over the Lower Level Road. Supreme Structural Transport was happy to be a part of the erection of the Stantec designed structure. The fabricator, Capitol Steel, was also pleased to see their handiwork installed safely over this North Shore roadway.
A King Post Support System was used in conjunction with hydraulic jacks and skid shoes to propel the bridge across the River without any in-stream temporary supports. Although the bridge is 80 meters in length, the critical part of the launch was the first 60 meters when the bridge was cantilevered over the river, until the south end of the bridge touched down on the pier. It is anticipated that the first 60 meters of travel will be completed in one day. (April 11th) The remaining 20 meters of travel requires a series of detailed and coordinated steps and is anticipated to take two to three days to complete.
Transport of the 650 tonne Shiploader unit included design of 70 tonne steel support frame which evenly distributed the load to the hydraulically floating 192 tires, development of the jacking procedure, and evaluation of the wharf structure’s ability to support the loads.
Mount Pleasant is one of the city’s most vibrant and fastest-growing neighbourhoods, with an anticipated local growth in electricity demand by almost 40 per cent in ten years, and 80 per cent in 30 years. To meet that growing need, BC Hydro commissioned construction of the new Mount Pleasant Substation; the first to be built in the city of Vancouver since 1984.
The team at Locher Evers International coordinated the trans-continental shipment of the two 140 ton Transformer Units and selected Supreme Structural Transport for their delivery from Shipside through the narrow Vancouver City streets to their new home in a 2-story building in the congested city centre.
Mount Pleasant is one of the city’s most vibrant and fastest-growing neighbourhoods, with an anticipated local growth in electricity demand by almost 40 per cent in ten years, and 80 per cent in 30 years. To meet that growing need, BC Hydro commissioned construction of the new Mount Pleasant Substation; the first to be built in the city of Vancouver since 1984.
The team at Locher Evers International coordinated the trans-continental shipment of the two 140 ton Transformer Units and selected Supreme Structural Transport for their delivery from Shipside through the narrow Vancouver City streets to their new home in a 2-story building in the congested city centre.
This colossal crane (dubbed “Hiyí Skwáyel”) is a critical component of Seaspan’s $200 million Shipyard Modernization Project, and will be the largest Gantry Crane in Canada, towering 80 metres high and spanning 76 metres wide. The new state-of-the-art facility will allow Seaspan to efficiently deliver Non-Combat Vessels for the Royal Canadian Navy and Canadian Coast Guard.
The crane components were delivered by ship to the Vancouver Harbour where SST received the components as they were craned onto three large barges. The barges were used to deliver the components to the new berth at the Seaspan Facility.
We are happy to announce we have our new website finally up and running. We’ve filled it with photos and videos from some of our biggest projects. You’ll also find detailed information about the services we offer. Have a read through our website and give us a call and let us know how we did.